The Executive Chairman of Nembe LGA has delivered on his promises of Infrastructural Development. He has also invested massively in marine transportation and by adopting the TWO-BY-TWO paradigm, touched all villages and Communities in Nembe Local Government.
This is not a shopping list but projects embarked upon by the Hon. Waribugo Sylva
1. Renovation of Intermediate Staff Qrts in Ogbolomabiri. This was awarded on August, 8th 2011 through direct labour and the job is 80% ,work in progress
2. Renovation of Intermediate Staff Qrts in Bassambiri. This was awarded on August, 8th 2011 through direct labour and the job is 80% ,work in progress
3. Construction of 100 units of chairs for Secondary School in Ologoama. This was awarded on December, 2011 through direct labour (2-2) and the job is 100% completed.
4. Purchasing of ferry Boats for School children in Emina Ama. This was awarded on December, 2011 through direct labour (2-2) and the job is 100% completed.
5. Purchasing of water pump and rehabilitation of Ologoama water Scheme in Ologoama. This was awarded on December, 2011 through direct labour (2-2) and the job is 100% completed.
6. Construction of Obioku Community Town Hall in Obioku. This was awarded on December, 2011 through direct labour (2-2) and the job is 100% completed.
7. Construction of Concrete walkway in Otumama. This was awarded on February, 2012 through direct labour (2-2) and the job is 100% completed.
8. Constructions of pier latrine in Ikensi. This was awarded on February, 2012 through direct labour (2-2) and the job is 100% completed.
9. Support for Chief Lionel Jonathan Omo Fishing Terminal---Waiting for Cash Donation
10. Construction of Landing Jetty in Eminama. This was awarded on May, 2012 through Pigatin and the job is 100% completed.
NEMBE LOCAL GOVERNMENT IS WORKING!